Lyon County Water District Sewer Project

Eddyville, Kentucky – Lyon County

 

Bacon Farmer Workman (BFW) was entrusted with the $0.9 million Lyon County Water District – Sewer Department project. The project consisted of:

  • 13,500 linear feet of 8” sanitary sewer
  • 2,500 linear feet of 10” sanitary sewer
  • 4,000 linear feet of 6” sewer lateral

To complete the project, BFW provided engineering services for the design and construction along with handling permitting with Division of Water and Army Corps of Engineers, public meetings, topographic surveys, and contract documents and specifications. BFW is proud to have assisted with the sewer addition project which provides sewer service for 130 plus residences located in Lyon County.

Milestones & Additional Tasks Included

  • Permitting with Division of Water and Army Corps of Engineers
  • Public Meetings
  • Topographic Surveys
  • Contract Documents & Specifications