Bacon Farmer Workman (BFW) took on the Old Sprigg Street Road Culvert Replacement project. The project required a wide variety of skills to replace a structurally deficient single span bridge structure with a box culvert for the Cape Special Road District, so BFW provided:
- Preliminary Engineering:
- Complete set of roadway and structure plans
- Specifications for a local letting
- Surveys:
- Topographic survey of the road and ROW
- Channel/floodplain cross-sections up- and down-stream of the crossing
- Submittals:
- Environmental Survey Request
- Preliminary Bridge Design and Hydraulic Report
- Submittals and coordination necessary to receive Corps of Engineers Permits
The Old Sprigg Street Road Culvert Replacement project cost $175,000 in total. BFW is proud to have been a part of the safety and function improvements to Old Sprigg Street Road.