This project involves the construction of a new overpass bridge for the extension of Ingram Road to the south of US60 as part of Sikeston’s industrial park development. Bacon Farmer Workman (BFW) was responsible for:

  • Administration:
    • Review CRE2O reports
    • Complete change orders, documentation of pay items, and generate estimates
    • Review and approval of subcontracts
    • Update local partners on construction activities
    • Maintain MoDOT’s stormwater database
    • Save documentation to MoDOT’s SharePoint site
    • Complete all applicable portions of AASHTOWare (AWP)
  • Contractor and Construction Administration:
    • Verify compliance with contract documents
    • Verify layout
    • Monitor quality control plan
    • Review payrolls
    • Manage traffic control for work zones
  • Inspections:
    • Construction
    • Contractor Performance
    • Material Testing
    • Erosion Control

In addition, BFW conducted QA and QC testing along with monitoring. BFW is proud to have managed the project to create a new overpass and expand the transportation capabilities of the Sikeston industrial park development.